General information, current at the date shown. It is not tax or legal advice: rules change and depend on your situation. Have your case checked by a Hungarian lawyer or accountant.
Key facts
- In Q2 2026 construction producer prices were 5.3% higher than a year earlier; prices of specialised construction work (electrics, plumbing, finishing) rose 5.8% [1][2].
- 2026 published guides: full renovation of a flat including services, about HUF 160,000/m² (basic), 240,000 (mid-range) and 380,000/m² (premium), furniture excluded [9].
- Cosmetic refresh of an average 60 m² flat: up to HUF 6 million; comprehensive energy renovation: up to HUF 15 million (2025) [7].
- Average building material prices fell 1.3% year on year in the first half of 2025 [8].
- For a listed building (műemlék), the heritage permit also covers interior works (layout, surfaces, doors and windows); processing time: 25 days [10].
What the published figures are worth
Hungary has no official survey of renovation costs per m². KSH (the Central Statistical Office) publishes a construction price index, not unit prices. Per-m² ranges come from the business press, analysts at estate agency networks, the builders' federation ÉVOSZ, and contractor platforms or guides. Their methods are rarely described and their scope differs: some include materials, others only labour; furniture, the fitted kitchen and design fees are often excluded [9].
These figures are therefore orders of magnitude. A reliable budget needs a survey of the existing condition and itemised quotes from several contractors. According to one 2026 guide, labour is typically 10–20% more expensive in Budapest than in the rest of the country [5]. The same type of guide recommends a contingency of about 15% [9].
| Item | Range (HUF) | Basis | Source |
|---|---|---|---|
| Electrics – full rewiring | 600,000–1,200,000 | 60 m² flat, 2026 | [5] |
| Electrics | 15,000–30,000 | per m², 2025 | [6] |
| Plumbing – water pipe replacement | 400,000–800,000 | 60 m² flat, 2026 | [5] |
| Plumbing | 20,000–40,000 | per m², 2025 | [6] |
| Heating – radiators and pipework | 500,000–1,500,000 | per flat, 2026 | [5] |
| Condensing gas boiler – replacement | 400,000–800,000 | per unit, 2026 | [5] |
| Bathroom (4–6 m²) – basic / mid / premium | 800,000–1,500,000 / 1,500,000–2,500,000 / 2,500,000–5,000,000+ | per room, 2026 | [5] |
| Kitchen – custom cabinets, mid / premium | 500,000–1,500,000 / 1,500,000–3,500,000 | per kitchen, 2026 | [5] |
| Granite or quartz worktop | 60,000–150,000 | per running metre, 2026 | [5] |
| Tiling – laying (labour) | 5,000–10,000 | per m², 2026 | [5] |
| Laminate – laying / material | 3,000–6,000 / 3,000–12,000 | per m², 2026 | [5] |
| Parquet | 12,000–25,000 | per m², 2025 | [6] |
| Painting – two coats, paint included | 2,500–5,000 | per m² of wall, 2026 | [5] |
| Painting – full preparation and painting | 5,000–10,000 | per m² of wall, 2026 | [5] |
| Window 150×150 cm tilt-and-turn, removal and fitting included | approx. 250,000 | per window, house, 2025 (ÉVOSZ) | [4] |
| Balcony door 90×210 cm | approx. 460,000 | per unit, house, 2025 (ÉVOSZ) | [4] |
| Radiator | approx. 90,000 | per radiator, 2025 (ÉVOSZ) | [4] |
Ranges by finish level
Published ranges for 2025–2026, labour and materials, per m² of floor area:
- Light refresh (painting, minor repairs, floors, switches): HUF 30,000–60,000/m² in a price compilation from April 2025 [4]; HUF 60,000–100,000/m² in a 2026 guide [5]. An estate agency network analyst put the cosmetic refresh of a 60 m² flat at up to HUF 6 million in 2025 [7].
- Full renovation (tiling, bathroom, kitchen, water and electrical networks): HUF 80,000–150,000/m² at mid level and HUF 150,000–300,000/m² for a complete renovation with services and windows (2025) [4]; HUF 100,000–180,000/m² [5], HUF 135,000–275,000/m² [6] and about HUF 240,000/m² mid-range with services [9] in 2026 sources. A comprehensive energy renovation of a 60 m² flat can reach HUF 15 million (2025) [7].
- High-end (new layout, custom joinery, premium materials): HUF 180,000–350,000/m² [5] and about HUF 380,000/m² [9] in 2026.
The gap between sources mostly reflects scope (services included or not, kitchen and furniture included or not) and the starting condition.
Costs by item
The table below lists item prices published in 2025–2026. In an old flat the heaviest items are usually electrics, plumbing and heating, because they involve chasing walls, re-plastering and coordination with the common risers. The bathroom and the kitchen vary most with the finish level.
Window prices come from ÉVOSZ data published in 2025 and refer to houses; in an old Budapest building, double-sash timber windows are often restored rather than replaced, and replacement can be restricted by protection rules [4][10].
Demolition and debris removal come on top: HUF 8,000–25,000/m² for demolition and HUF 150,000–200,000 to remove 15–20 m³ of debris from a 60 m² flat [6]. In the city centre, a missing lift, parking and renting a skip on the street add to this item.
Construction price trend
The KSH construction producer price index measures year-on-year change, quarter by quarter [1]:
- Total construction: +6.7% in Q1 2024, +5.7% in Q2 2025, +5.1% in Q4 2025, +4.7% in Q1 2026, +5.3% in Q2 2026.
- Buildings: +4.5% in Q2 2026.
- Specialised construction work (electrical and plumbing installation, finishing, demolition): +6.5% in Q2 2025, +5.4% in Q1 2026, +5.8% in Q2 2026.
The Q1 2026 increase was the smallest since Q2 2017 [3]. In Q2 2026 prices were on average 1.9% higher than in the previous quarter [2]. Q3 2026 data had not yet been published on 26 October 2026.
Materials were not the main driver in 2025: their average prices fell 1.3% in the first half of 2025, and price moves in imported products mostly followed the exchange rate [8]. According to the May 2026 sector review, labour, material and subcontractor costs continue to push prices up [3]. Companies surveyed in April 2026 expected further price rises (balance of +27.6 points) [3]. For a project starting in six to twelve months, it is prudent to index quotes to this trend.
What drives costs in old buildings
- Common parts and the condominium's consent: load-bearing walls, floor slabs, light wells (lichthof) and water or heating risers are common property, even inside the flat. Since the 2021 amendment of the Condominium Act, such works require the general meeting's consent, based on plans and a structural engineer's opinion [11]. Budget for the engineer, the time to vote and any conditions set by neighbours.
- Building permits: building authority procedures are governed by Government Decree 281/2024 (IX. 30.), applied since October 2024 [12]. Works carried out without a required permit in the last ten years are regularised through the building permit procedure [12]. Have an architect confirm whether your project needs a permit.
- Protected buildings: for a műemlék, a heritage permit is needed not only for the facade, windows and roof but also for the interior layout, surfaces, doors and windows, decorative elements and the flat's installations; processing time 25 days, validity one year [10]. District regulations can set stricter rules for locally protected buildings [13].
- Old installations: original wiring, risers at the end of their life and flues that must be brought up to standard often mean replacing everything rather than repairing.
- Logistics: buildings without a lift, narrow streets, working hours set by the house rules, and debris removal [6].
Rule of thumb: commission a survey (structure, services, damp) before agreeing the purchase price, since renovation cost directly reduces the margin.
Frequently asked questions
Why do per-m² ranges differ so much between sources?
Because the scope differs: services, kitchen, furniture and design fees may or may not be included, and the starting condition varies. None of the published sources describes a survey method [9].
Will prices keep rising?
The latest KSH data show a 5.3% year-on-year rise in Q2 2026 [1], and companies expected further increases in April 2026 [3]. No official numerical forecast is published for renovation work.
Do I need a permit to remove a partition wall?
A non-load-bearing partition is usually part of the flat. If the wall is load-bearing or affects a common part, the general meeting's consent and a structural engineer's opinion are needed [11]; in a műemlék, a heritage permit also applies to changes to the interior layout [10].
Sources
- KSH STADAT 1.2.1.25. – Az építőipar termelőiár-indexei, negyedévente — seen on 26 October 2026
- KSH Gyorstájékoztató – Építőipar, 2026. június (2026.08.13.) — seen on 26 October 2026
- MGFÜ – Havi ágazati kitekintő: építőipar (2026.05.29.) — seen on 26 October 2026
- Világgazdaság – Ennyibe kerül most a lakásfelújítás és az építkezés (2025.04.01., ÉVOSZ-adatokkal) — seen on 26 October 2026
- Teljeskivitelezes.hu – Mennyibe kerül egy lakásfelújítás 2026-ban? — seen on 26 October 2026
- ÁrBázis – Mennyibe kerül egy lakás teljes felújítása négyzetméterenként? (2025.11.29.) — seen on 26 October 2026
- Economx – Már a felújítandó ingatlanok négyzetméterára is karcolja a milliót (2025.06.17.) — seen on 26 October 2026
- Economx – ÉVOSZ Építőanyag-kereskedelmi Tagozat: 2025. első félév (2025.08.15.) — seen on 26 October 2026
- Építcentrum – Teljes felújítás 2026: lakás és családi ház ára — seen on 26 October 2026
- Kormányhivatalok – Tájékoztatás az örökségvédelmi engedélyezési eljárásról (műemlékvédelem) — seen on 26 October 2026
- Világgazdaság – Lakásfelújítás társasházban: a közgyűlés hozzájárulása a 2021-es módosítás óta — seen on 26 October 2026
- Decs Nagyközség Önkormányzata – Lakossági tájékoztató a 281/2024. (IX. 30.) Korm. rendelet szerinti építésügyi szabályokról — seen on 26 October 2026
- Privátbankár – Vaskos bírság a lakásfelújítás miatt: társasházi és helyi szabályok — seen on 26 October 2026